Combined with the above analysis, in order to prevent the recurrence of the diversion parallel groove clamp accident in the later line operation, the following measures are proposed.
4.1 Carefully handle the parallel groove connector contact surface during construction and maintenance. In addition to the contact surface being flat and smooth, it is more important to apply power composite grease and remove the oxide layer. Power composite grease can form a protective film on the contact surface to prevent the infiltration of water electrolyte and isolate the oxidation effect of air, thereby increasing conductivity and reducing contact resistance, and delaying the aluminium pg clamp deterioration process.
4.2 Select a suitable contact pressure. Since the contact resistance is inversely proportional to the total contact pressure, when bimetal pg clamp reaches a critical pressure value, the pressure will increase again, which will cause the material to deform and the contact resistance will increase instead. Therefore, blackburn parallel groove clamp should be tightened with a torque wrench during installation, and a reasonable quantitative regulation of the tightening pressure should be made at the same time.
4.3 It is recommended that aluminum burndy parallel groove clamp should not be used for the drainage wire joints of heavy-load lines and JL/G1A-150 and above conductors in dirty areas. Point contact should be avoided as much as possible, and surface contact should be used instead. Compressible equipment wire clamps should be used to increase the contact area, and electrical composite grease should be applied to prevent contact surface oxidation and increased contact resistance due to dirty substances.
4.4 Strengthen inspections during operation. For heavy-load lines, use infrared thermal imagers to measure the temperature of contact points to determine whether there are hidden defects at the connection points.
4.5 Strictly follow the construction specifications and construction standards, grasp the acceptance of new, modified and expanded projects, and take the connection points as the acceptance focus.
4.6 Adjust the operation mode, try not to overload operation, and keep the operating temperature no more than 80℃.